Condominium dorm for growing Tamaraws and Tigers
This is the proposed positioning and MVP for the Corte Fragata Eloisa condominium
Condominium dorm for growing Tigers and Tamaraws. Walking distance from UST and FEU. A great and homely home away from home
Huwebes, Disyembre 19, 2013
Status of Finishing Work at Corte Fragata
Home for Tamaraws and Growling Tigers
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"
Corte Fragata Almost 98% finished
Home for Tamaraws and Growling Tigers
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"
Mga etiketa:
2013,
construction meeting,
December 17
Biyernes, Nobyembre 1, 2013
Prices of Corte Fragata are competitive - very competitive for nearly finished project
I sat next of a property consultant of Picar and they sell among other projects condo project near Makati Av (A venue) and she told me that the average selling price of their projects is P3 m for a 26 sm studio. That is way way ahead of the 22 sm for P2.6 million of Corte Fragata considering that their price is pre selling price
Come and visit Corte Fragata soon.
Come and visit Corte Fragata soon.
Linggo, Oktubre 13, 2013
Pictures of the development
A staggering P700t worth of materials has been spent on the 9th floor and much is very visible and which contributed to the 4% weighted development of the project. This excludes about the P400t which has been spent on labor (but much of that is on finishing)
Wall near the stair from 8th floor
Steelworks for the beam
Ingenious formworks
Many columns are up
See the invented clamps
Concrete ledges in lieu of polycarbonate for shade and sunlight protection
Linggo, Setyembre 29, 2013
Our goal is to finish Corte Fragata by November 23, 2013 time of Angono Town Fiesta
1151 Eloisa Sampaloc Manila PHL September 28, 2013
We met with the workers, engineers and funders for the final completion of Corte Fragata.
Some of noteworthy news:
1. The works last week September 22 to 28 amounted to 3% of the total project cost; that is amazing since that period covered only 6 days;
2. There are 34 workers at the site and more than half million worth of materials have been purchased and delivered for only one week.
3. Next week, the electrical materials and more finishing materials for the 6th to 8th floor will be bought; the 9th floor (topping off portion is in full blast)
4. There was a walk in buyer who is interested at the 4th floor.
5. There will be t shirts, tarp at the site, and prizes for workers in case the project % are met on certain dates.
Some refreshments and food were served to the workers at the end of the meeting
Congratulations to Sir Frank and his team for job well done
We met with the workers, engineers and funders for the final completion of Corte Fragata.
Some of noteworthy news:
1. The works last week September 22 to 28 amounted to 3% of the total project cost; that is amazing since that period covered only 6 days;
2. There are 34 workers at the site and more than half million worth of materials have been purchased and delivered for only one week.
3. Next week, the electrical materials and more finishing materials for the 6th to 8th floor will be bought; the 9th floor (topping off portion is in full blast)
4. There was a walk in buyer who is interested at the 4th floor.
5. There will be t shirts, tarp at the site, and prizes for workers in case the project % are met on certain dates.
Some refreshments and food were served to the workers at the end of the meeting
Congratulations to Sir Frank and his team for job well done
Biyernes, Setyembre 27, 2013
Wowing them with Corte Fragata website
When we were securing additional funding for the speedier financing of this condo project, all we had to do was to give them the website and the link. And we were able to wow them instantly. A website, blogsite gives the project instant recognition and credibility. But of course, the track record of the one who leads the project, the ability to keep up with the promises on time builds the credit and the trust of the various stake holders.
And we are happy that we have that trust and confidence. That we can deliver and we can keep our promises
And we are happy that we have that trust and confidence. That we can deliver and we can keep our promises
Mga etiketa:
confidence,
credibility,
trust,
website,
wow
Mag-subscribe sa: