Status of Finishing Work at Corte Fragata
Home for Tamaraws and Growling Tigers
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"
Corte Fragata Almost 98% finished
Home for Tamaraws and Growling Tigers
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"
1151 Eloisa, Sampaloc, Manila Philippines | December 19, 2013
It is 6 days before Christmas. We had our construction progress meeting last December l7, 2013 with the owner and the project engineer. All the materials have been purchased, and only expenses will be the labor. The roofing will have to be installed, all the floors will have to be 5s; there will be less dirt and disorderliness when the materials transport is finished.
By next week, all floors until the 5th will have been presentable to buyers. It is time to focus on the marketing. As of now, from the external, to the buyers, nothing looks to have changed
The positioning that looks relevant to the users now is that of "condominium dormitory for UST and FEU students"